Raheenleagh Electrical Balance of Plant

Raheenleagh  Electrical Balance of Plant

Project Name:

Raheenleagh Electrical Balance of Plant

Client:

ssr_e_sml

Project Deliverables:

Raheenleagh Wind Farm will have a maximum Export Capacity of 36.5MW. The Project consists of 11 turbines on a site that is owned by Coillte located in Wicklow. The project comprises 38kV electrical substation at the Raheenleagh site and approximately 1.4 km of 38 kV underground cable routes that falls within the site boundary connecting it to the 110 kV busbar at Arklow 220kV station via a new 63MVA transformer at Arklow.

Scope of Works includes;

  • Design, supply, install and pre-commission the 38kV DSO receiver station to DSO requirements,
  • Design, supply, install and pre-commission and commission the 38kV/20kV IPP station including buildings, power transformer and 20kV board to client’s standards and requirements,
  • Design, supply, install and commissioning of the 20kV collector system up to switchboard inside each wind turbine,
  • Interfacing with all wind turbine systems as required.
afaquvdb